Permit guide · SDCI

Getting an SDCI Permit for a Seattle Mezzanine: Portal, Plan Review and Inspections

A new mezzanine inside Seattle needs a construction permit from the Seattle Department of Construction and Inspections (SDCI). Because it is structural work, it goes through plan review, not the quicker field-inspection permit. Here is SDCI's process in order, from the Seattle Services Portal to the final inspection.

Green steel mezzanine spanning wall to wall across a narrow hall, with yellow guardrail and a stair along one wall

Do You Need an SDCI Permit to Add a Mezzanine in Seattle?

Yes. Seattle Building Code Section 106.1 requires a building permit "prior to erecting, constructing, enlarging, altering, repairing, moving, improving, removing, changing the occupancy of, or demolishing" a building or structure. A new mezzanine is erected inside an existing building, so it is covered. The code's small-work exemption does not help either. It covers minor work valued at $6,000 or less in six months, but excludes "the removal, reduction, alteration, or relocation of any loadbearing support." A steel deck is loadbearing from the first column. Our Seattle mezzanine permits and code guide covers the code rules that plan review checks.

Is a Seattle Mezzanine an STFI Permit or a Plan Review Permit?

Plan review, in almost every case. SDCI's subject-to-field-inspection (STFI) permit is for small projects, such as "interior non-structural alterations to an existing commercial space." Its checklist says that if any listed item applies, "your project will require plan review." Several items can describe a new mezzanine:

  • "Work involves structural work."
  • "Additions of new floor area."
  • "Work is in more than 4,500 sq. ft. of floor area."
  • "Change in number of exits; change in path of travel or distance to exits."

Seattle's permit records point the same way. Of 62 permits since 2019 that mention a mezzanine, 59 are the Addition/Alteration type. STFI shows up only for work on a mezzanine that already exists. SDCI decides the permit path for your project at screening.

What Are SDCI's Steps for a Commercial Mezzanine Permit?

Six steps, all online. SDCI says its "permit counters are closed, and permits are no longer being issued in person or on the day of your application." Its addition and alteration page sets out the order below, in our words. Once SDCI accepts the pre-application, you receive a construction record number ending in -CN.

  1. Research. Look up the property on the City's GIS map and its permit history in the Seattle Services Portal.
  2. Pre-application. Start a Building & Land Use Pre-Application in the portal with a site plan. A site visit is needed if you disturb more than 750 sq ft of land or any land on a critical-area site. A pre-submittal conference is optional for complex projects.
  3. Screening and intake. SDCI screens the application, and you book an electronic intake appointment. "You must upload all application documents by 7 AM on the day of your appointment." You pay about 75 percent of the fees and answer corrections.
  4. Issue. Pay the final fees, then print and display the permit.
  5. Inspections. Request each inspection as the work reaches it.
  6. Certificate of occupancy. SDCI lists this step only "if you have changed the use of, or number of residences in, your building."

Who Prepares and Seals the Drawings for a Seattle Mezzanine?

A Washington-licensed architect or structural engineer. SBC 106.5.2 says construction documents are "prepared and designed by or under the direct supervision of an architect or structural engineer licensed to practice under the laws of the State of Washington." That professional seals and signs each sheet before the permit is issued. SDCI's Tip 100 adds that licensed designers are needed for any project valued at $75,000 or more. We do not seal drawings. We give the engineer the layout, the loads and the site measurements, and we coordinate the submittal with them.

The drawings also carry Seattle-specific items. The first sheet lists the "Number of stories above grade plane, mezzanines and basements." The structural notes list snow, live and lateral design loads.

What Does SDCI Plan Review Check on a Mezzanine?

The deck's size, height, exits, access and structure, each against the Seattle Building Code. A reviewer reads the sealed drawings section by section. The list below is where a mezzanine usually draws questions. Each item has its own section number, so a correction notice is easy to trace. Answering in the same terms keeps each round short. Our guides to Seattle's one-half area rule and mezzanine seismic design go deeper on two of them.

  • Area: mezzanines in a room may total one-half of its floor area inside Seattle (SBC 505.2.1).
  • Height and openness: the 7-foot clear height rule on both levels, and no walls over 42 inches toward the room unless an exception fits (505.2, 505.2.3).
  • Exits: mezzanines count as spaces needing exits under Section 1006.2.
  • Access: an accessible route to the mezzanine unless an exception in Section 1104.4 applies.
  • Structure: design loads, and earthquake design under Section 1613.

How Long Does SDCI Take to Review a Mezzanine Permit?

SDCI states a goal, not a fixed time. Its addition and alteration page says: "We try to finish our initial review of simple permit applications in two-three weeks and complex permits in eight weeks." That is SDCI's stated target for a first review. It is not a promise from us, and it is not a measure of today's actual times. Corrections add rounds after that first review. SDCI's Tip 100 also advises starting the pre-application "two to three months before your project will be ready to submit to SDCI for intake." We build both into the schedule we plan with you.

SDCI Timing Statements for a Commercial PermitSDCI, Construction Permit: Addition or Alteration; SDCI Tip 100 (updated July 9, 2024).
StageWhat SDCI saysSource
Before intakeBegin the pre-application two to three months before you are ready to submitTip 100
Intake dayAll documents uploaded by 7 AMAddition or Alteration page
Initial review, simple permitsGoal of two to three weeksAddition or Alteration page
Initial review, complex permitsGoal of eight weeksAddition or Alteration page
After issuePermit valid for 18 months after the issue dateAddition or Alteration page

How Does SDCI Charge Fees for a Mezzanine Permit?

By the value of the project, in two payments. SDCI says: "Fees are based on the value of your project. You pay approximately 75 percent of your fee when you submit your plans and the rest when you pick up your permit." It also charges hourly fees for certain reviews, such as drainage and geotechnical. SDCI publishes a fee estimator on its site. We do not quote permit fees, because SDCI sets them from your project's value. Our mezzanine cost guide lists the other Seattle cost drivers to plan for.

What Happens After SDCI Issues the Permit?

The work starts, and inspections follow it. SDCI says the permit "is valid for 18 months after the issue date," and it must be printed and displayed on site. Under SBC 108.1, permitted work "is subject to inspection by the building official." Some items also need special inspection by registered special inspectors under Chapter 17. Section 108.7 calls for "a final inspection and approval of all buildings when completed and ready for occupancy." Our crew walks the inspector through the frame, anchors, stairs and rails.

Seattle also ties load signs to occupancy. Where a certificate of occupancy is needed, SBC 107.2 holds it until the floor load signs are up. Read Seattle's load-posting rule for what the signs show.

Large free-standing galvanised steel mezzanine with yellow guardrail and two stairs, shelving of boxes on the deck, seen from above
Illustration: a finished free-standing mezzanine with stairs and guardrail, the stage at which the final inspection is requested.

What Do Seattle's Permit Records Show About Mezzanine Work?

They show steady demand, mostly in commercial and industrial buildings. The City's open data lists 62 permits applied for since January 1, 2019 that mention a mezzanine. Of those, 55 are Commercial or Industrial class. ZIP codes 98134 and 98104 lead with six each, and 98108 follows with five. Parts of SODO and Georgetown fall in 98134 and 98108. Descriptions range from new mezzanines for office and storage space to extending a deck across a warehouse. Some records remove an old mezzanine and its stair. None of these records are our projects. They simply show how often this work is filed in Seattle.

What Do We Handle on a Seattle Mezzanine Permit?

The layout, the coordination and the build; the engineer seals and SDCI decides. We measure the room and settle the deck, loads, stairs and gates with you. We hand that package to a Washington-licensed engineer, who prepares and seals the drawings. We help assemble the submittal and track SDCI's corrections with the engineer. Once the permit is issued, we deliver the steel and our installers erect it. Then we book the inspections in order.

The steel waits for the permit. We do not start building before SDCI issues it.

SDCI Permit Questions, Answered

Can I apply for a mezzanine permit in person in Seattle?

No. SDCI says its permit counters are closed and permits are no longer issued in person. You apply through the Seattle Services Portal, starting with a pre-application.

Source: SDCI, Construction Permit: Addition or Alteration

How long is a Seattle building permit valid?

SDCI says a permit is valid for 18 months after the issue date. Plan the build so the work and its inspections fall inside that window.

Source: SDCI, Construction Permit: Addition or Alteration

Does a mezzanine in Seattle need drawings sealed by an engineer?

Plan on it. SBC 106.5.2 has construction documents prepared by an architect or structural engineer licensed in Washington, who seals each sheet before the permit is issued. Its exceptions cover nonstructural work under $75,000 and certain designed specialty products, and plan review decides whether one applies.

Source: 2021 Seattle Building Code, Section 106.5.2

Sources, read November 2026: Seattle Building Code 2021, Chapter 1 (permits, documents, load signs) · SDCI, Construction Permit: Addition or Alteration · SDCI, Construction Permit: Subject-to-Field-Inspection · SDCI, Multifamily and Commercial STFI Checklist · SDCI Tip 100, Getting a Multifamily or Commercial Construction Permit · City of Seattle open data, Building Permits (mezzanine records since 2019)